Marshfield Medical Center's new USP 797/800 sterile compounding suite passed certification on the first attempt and earned State Board of Pharmacy approval, even after the project's footprint nearly doubled midway through design. Aero Performance Group's Critical Environment Division delivered the 1,735-square-foot ISO 7 suite as the design-build partner, from site evaluation through move-in, with relocation downtime effectively eliminated.
Get the full case study
Photos, the complete project narrative, and room conditions at handover in a printable PDF.
| Detail | Result |
|---|---|
| Client | Marshfield Medical Center, Marshfield Clinic Health System |
| Location | Marshfield, WI |
| Space | USP 797/800 sterile compounding suite, ISO 7 |
| Size | 1,735 square feet; 3 classified rooms |
| Hoods | 3 hazardous biological safety cabinets (BSCs); 7 non-hazardous BSCs and laminar airflow workbenches (LAFWs) |
| Delivery | Design-build, Aero Performance Group's Critical Environment Division |
| Timeline | December 2025 to October 2026 |
| Outcome | First-time pass; State Board of Pharmacy approval |
Sterile compounding sits at the center of patient care. IV medications and other compounded sterile preparations (CSPs) depend on a space that meets USP 797, and USP 800 when hazardous drugs are involved. Marshfield Medical Center set out to build a compliant suite for Category 2 CSPs so its pharmacy could keep serving patients with confidence.
The original plan called for a focused compounding suite. During design, hospital leadership saw a larger opportunity: bring several pharmacy departments together in one state-of-the-art space.
That decision nearly doubled the facility's footprint and added hazardous drug (HD) receiving, HD storage, and non-sterile HD compounding to the program. Every element of the plan, from airflow to room layout to the move-in sequence, had to scale with it.
As the design-build partner, Aero's Critical Environment Division carried a single line of accountability across every phase. The team started with an evaluation of the existing site, then planned the full compounding suite, including HD receiving and storage and non-sterile HD compounding.
Aero developed the project specifications and provided mechanical design consulting, including the airflow diagram, critical component selection, and submittal review. Specified components included air valves, HEPA fan filter units (FFUs), hand-wash sinks, pass-throughs, and the cleanroom wall system.
The airflow diagram revealed an important opportunity. HEPA fan filter units provide localized recirculation inside the suite, delivering the required air changes while the existing mechanical systems stay in service. The hospital kept its air handlers and put its budget into the space itself.
That matters because air change requirements are demanding. According to the American Industrial Hygiene Association, an ISO 7 space must receive a minimum of 30 air changes per hour (ACPH), compared with 20 ACPH for an ISO 8 anteroom.
Smooth, crevice-free finishes support a cleaner aseptic environment and make daily cleaning faster. Hood placement and mobility shape how well staff can meet USP 797 cleaning requirements, so Aero planned both around the pharmacy team's workflow.
Aero built the entire cleanroom suite, including walls, doors, windows, and pass-throughs. The team provided and started up the HEPA fan filter units with BACnet integration into the building automation system (BAS) and supported the BAS contractor during air valve startup.
A pharmacy display monitor now shows staff live room pressure, temperature, humidity, and air changes, along with fan filter unit status and refrigerator and freezer temperatures.
Consolidating departments meant the pharmacy had to keep compounding throughout the transition. Aero developed an occupancy plan that sequenced punchlist completion, test and balance, sterile cleaning, certification testing, and move-in.
Aero also recommended purchasing new hazardous drug BSCs, so the new suite could open on schedule while the existing hoods stayed in service. Relocating the old HD hoods would have required decommissioning, moving, balancing, and certifying each one. That single decision shortened the transition and effectively eliminated relocation downtime. Aero's team then supported the relocation of the existing non-hazardous hoods into the new suite.
| Room | Pressure (in. w.c.) | Air Changes per Hour |
|---|---|---|
| Ante room | +0.03 | 35 |
| Non-hazardous buffer room | +0.04 | 35 |
| Hazardous drug buffer room | −0.02 | 42 |
| Hazardous drug receiving room | −0.02 | 15 |
Today, Marshfield Medical Center runs multiple compounding operations from one consolidated suite, with the efficiency and oversight that come with a single, purpose-built space.
"Thank you Mike for your expertise and professionalism with this project. You and your team brought a surplus of value to ensure this complex process went smoothly."
Robert Dubiel, CHFM, CHC, Head of Construction, Design and Construction, Marshfield Clinic Health System
A USP 797/800 compounding suite is a pharmacy cleanroom built to meet USP Chapter 797 standards for compounded sterile preparations and USP Chapter 800 standards for handling hazardous drugs. The suite typically includes ISO-classified buffer rooms for compounding and anterooms for gowning, with controlled pressure and HEPA-filtered air changes in each room.
Aero Performance Group's Critical Environment Division delivered a 1,735-square-foot ISO 7 sterile compounding suite with three classified rooms as the design-build partner. The scope covered site evaluation, specifications, mechanical design consulting, cleanroom construction, fan filter unit startup and BAS integration, and the occupancy and move-in plan.
HEPA fan filter units provide localized recirculation inside the suite, delivering the required air changes while the hospital's existing mechanical systems stay in service. At handover, the buffer rooms measured 35 to 42 air changes per hour, above the 30 ACPH minimum for ISO 7 spaces.
Aero recommended purchasing new hazardous drug biological safety cabinets, so the new suite could open while the existing hoods stayed in service. Combined with an occupancy plan that sequenced punchlist, test and balance, sterile cleaning, certification, and move-in, that decision effectively eliminated relocation downtime.
Yes. The suite passed USP 797/800 requirements on the first attempt, achieved ISO 7 classification with more than 35 air changes per hour, and received State Board of Pharmacy approval for use.
Planning a new compounding suite, expanding an existing one, or preparing for a USP 797/800 inspection? Aero Performance Group's critical environment specialty contracting team guides healthcare pharmacies from first sketch to Board approval, with cleanroom services that support the space after move-in.
For the complete project story, download the full Marshfield Medical Center case study (PDF).